Otak was the lead consulting engineer for Wildish Standard Paving on this $40 million design-build project along US395 in Eastern Oregon. Spanning nearly half the state, this project included replacement of seven bridges along a sensitive waterway and wild and scenic corridor. Otak provided construction surveying for all phases of bridge construction. Field staking and verification tasks included layout of all bridge piers, piles and abutments; layout of retaining and wing walls; staking of impact panels, guard rails, paving, signing and striping; measurement of beam cambers and deflections; staking of site grading and water quality facilities; control and verification for prefabricated bridge assemblies; rail control for bridge deck placement and facility as-built data.