Client: Wildish Standard Paving, Inc.

Otak was the lead consulting engineer for Wildish Standard Paving on this $40 million design-build project along US395 in Eastern Oregon. Spanning nearly half the state, this project included replacement of seven bridges along a sensitive waterway and wild and scenic corridor. Otak led a multi-disciplinary project team to develop plans, specifications and a quality assurance and inspection program for construction. Bridge replacements were constructed in multiple stages to accommodate continuous traffic, or as rapid construction with offsite detours. Construction management, inspection and quality assurance services were provided over the course of the two-year long construction duration. Otak provided the quality and quantity documentation and inspection per ODOT and FHWA requirements for this federally funded project.