As part of the ACEC and ODOT Region 2 Brown Bag Lunch Series, Scott Banker, Melanie Klym, and Chad Maxwell gave a presentation on the US20: Pioneer Mountain-Eddyville (PME) Environmental Mitigation Measures. Environmental mitigation measures for stream and wetland impacts associated with the construction of the US20 PME project were constructed during 2016 and 2017, with additional habitat enhancement measures to be completed by the end of 2017. 

The contractor moved approximately 74,000 cubic yards of existing material, isolated creeks to perform channel grading and installed large wood structures. Mitigation efforts also included roughly 25 acres of planting and seeding. The presentation reviewed the unique aspects of the design and primarily focused on the challenges of constructing a large-scale mitigation project using traditional ODOT plans and specifications.