December 2015

Otak responded to an emergency for long time client Clark Regional Wastewater District (CRWWD).
On Dec 8th, Clark County was inundated with a terrific rainstorm that caused flooding and damage. During the event a small landslide broke a sewer line pipe along Tenny Creek. On Dec. 9 Otak acted quickly to stabilize the situation and provided immediate support with survey crews, hydraulic analysis, stream design, slope stabilization design, restoration planting design. Design documents and permitting were completed by Dec. 15th and construction began on Dec. 16. Currently, the contractor has cleared the area, installed the temporary stream bypass, repaired the broken sewer line, and has begun excavation for the stabilization work. The project is expected to be complete before the end of the year.