US395: McKay Creek to Silvies Slough Design-Build Bundle 414

Location: OR
Client: Wildish Standard Paving, Inc.

Otak is the lead consulting engineer for Wildish Standard Paving on this $40 million design-build project along US395 in Eastern Oregon. Spanning nearly half the state, this project includes replacement of seven bridges along a sensitive waterway and wild and scenic corridor. Otak led a multi-disciplinary project team to develop plans, specifications and a quality assurance and inspection program for construction. Bridge replacements were constructed in multiple stages to accommodate continuous traffic, or as rapid construction with offsite detours. Construction management and inspection services were also provided.